ILLUSTRATIVE EXECUTION SCOPE · REPRESENTATIVE PROJECT FRAMEWORK · AE-07
MSEDCL HT Load Sanction & CEIG Charging Approval
Representative framework for managing end-to-end Maharashtra MSEDCL HT load enhancement (11kV/22kV) and Chief Electrical Inspector (CEIG) drawing approval through official energization permission.
Framework Disclosure:
AE-07 is published as an Illustrative Execution Scope / Representative Project Framework detailing AAROHAN ELECTRICALS' standardized execution sequence, applicable IS/IEC standards, and handover deliverables.
Division E4 · Statutory Liaison
Technical Framework Parameters
| Utility / Authority | MSEDCL & CEI Office, Govt. of Maharashtra |
| Voltage Class | HT 11 kV / 22 kV / 33 kV Industrial / Commercial |
| Key Statutory Forms | CEI Layout Approval, Form A, GRAS Challan |
| Compliance Baseline | CEA Safety Regulations, 2023 & MERC Code |
EXECUTION & TESTING DELIVERABLES
Standardized Site Execution Sequence
- Preparation of load schedule, SLD & substation layout drawings for CEI & MSEDCL submission
- Online portal filing, technical feasibility follow-up & demand note verification
- Site readiness audit: safety clearances, rubber mats, danger boards, earthing & oil BDV reports
- Licensed Contractor Form A completion certificate & test dossier submission
- Physical inspection coordination with CEIG officer & obtaining official Charging Permission