ILLUSTRATIVE EXECUTION SCOPE · REPRESENTATIVE PROJECT FRAMEWORK · AE-03
PCC & MCC Panel Fabrication & Installation
Representative framework for engineering, fabricating, inspecting, and commissioning compartmentalized IP54 Power Control Centres (PCC) and Motor Control Centres (MCC) for industrial manufacturing floors.
Framework Disclosure:
AE-03 is published as an Illustrative Execution Scope / Representative Project Framework detailing AAROHAN ELECTRICALS' standardized execution sequence, applicable IS/IEC standards, and handover deliverables.
Division E2 · LT Panels
Technical Framework Parameters
| Construction Standard | IS 8623 / IEC 61439, 14/16 SWG CRCA, IP54 |
| Incomer / Fault Level | 1250A Draw-Out ACB, 50 kA for 1 sec |
| Motor Feeders | DOL, Star-Delta, Soft-Starter & VFD Bays |
| Metering & Safety | Digital MFM (RS-485), Shrouded Busbars, Earth Bar |
EXECUTION & TESTING DELIVERABLES
Standardized Site Execution Sequence
- GA & SLD drawing approval with feeder schedules, busbar cross-section & cable alley sizing
- 7-tank powder-coated enclosure fabrication with neoprene gaskets & vermin-proof louvers
- Factory Acceptance Test (FAT): 2.5 kV HV dielectric test, functional trip & interlock checks
- Base channel grouting, panel erection, cable dressing & IS 15652 insulating rubber mat placement
- As-built panel schematic & breaker setting schedule handover